Eurasian Resources Group (ERG) has postponed the construction of a hot briquetted iron (HBI) plant in the Kostanay region due to changes in the global market and raw material quality requirements. The project is not canceled, and ERG will not pay penalties to suppliers and contractors for the delay. ERG clarified that financing from the Development Bank of Kazakhstan up to $400 million was discussed within the framework of the project development.
The key project for ERG today is the construction of a new modern pelletizing plant with a capacity of 5 million tons per year. In Rudny, where SSCPO is located, preparations are underway for the construction of a new iron ore pellet plant.
QazaqGaz is carrying out its modernization, which will allow increasing capacity and, in the future, possibly provide the HBI plant with the necessary volumes of gas.
Project: Kostanai HBI plant · Kazakhstan · Planned
Key facts
- ERG postponed the construction of a large HBI plant in the Kostanay region.
- The postponement is due to global market changes and raw material quality requirements.
- ERG will not pay penalties to suppliers and contractors for the delay.
- Financing from the Development Bank of Kazakhstan up to $400 million was discussed.
- QazaqGaz is modernizing infrastructure to potentially supply gas to the HBI plant.