Kazakhstan: Eni Plenitude plans 100-MW wind farm Badamsha-3 in Aktobe region

Investors, volumes and stages of the region's major projects – for European suppliers

· 2 Sources

Scroll
Energy Kazakhstan2 Sources

Published · last updated · 16 Sep 2026 – 17 Sep 2026

Eni Plenitude intends to build a 100-MW wind farm in Kazakhstan's Aktobe region. The project, named Badamsha-3, has a volume of $100 million. Construction is scheduled to begin in 2027, with commissioning planned for 2028.

Eni Plenitude plans to build a new wind power plant with an installed capacity of 100 MW in the Aktobe region. The project is named Badamsha-3 and has an estimated volume of $100 million. The final investment decision is expected in the coming months. Construction is scheduled to begin in 2027, with commissioning planned for 2028.

A 1,000-hectare land plot has been allocated for the implementation, and internal preparatory work is already underway. Approximately 30 jobs will be created during the construction phase, and around 150 permanent jobs will be created after commissioning. The project expands Eni Plenitude's renewable energy portfolio in the region, where wind farms Badamsha-1 (48 MW, commissioned 2020) and Badamsha-2 (48 MW, commissioned September 2021) are already operating.

During a meeting between the Governor of the Aktobe region, Askhat Shakharov, and Alessandro Della Zoppa, Head of Renewable Energy at Eni Plenitude, further steps were coordinated. Shakharov emphasized the region's interest in developing renewable energy and the authorities' readiness to support the investor within the framework of applicable legislation. Della Zoppa mentioned that Eni Plenitude uses battery storage systems worldwide and is exploring the potential use of such systems in future projects in Kazakhstan.

Project: Badamsha-3 wind farm · Kazakhstan · Planned · $100 m

Key facts

  • Investment volume: $100 million
  • Installed capacity: 100 MW
  • Construction start: 2027
  • Commissioning: 2028

All sources (2)

  1. Eni Plenitude построит в Актюбинской области новую ВЭСKapital.kz · · RU
  2. Eni Plenitude plans to build 100-MW wind farm in Kazakhstan's Aktobe regionTrend News Agency · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn