Kazakhstan: Construction begins on waste recycling and steel plant in Taldyqorghan

Investors, volumes and stages of the region's major projects – for European suppliers

· 6 Sources

Scroll
Construction & cities Kazakhstan6 Sources

Published · last updated · 28 Jul 2026 – 3 Aug 2026

Construction has commenced on two industrial facilities with a total volume of $305 million in the Taldyqorghan industrial zone in the Taldyqorghan region. The projects include a solid municipal waste recycling facility and a steel plant, to be realized in joint ventures with South Korean and Chinese partners respectively.

Construction start and investment volume

Construction has commenced on two major industrial facilities in the „Taldyqorghan“ industrial zone in the Taldyqorghan region. The foundation laying ceremony was attended by the Akim of the region, Erbol Karashukayev. The total investment for both projects amounts to $305 million. The implementation is part of state directives aimed at economic diversification, development of the manufacturing industry, and ensuring environmental security.

Waste recycling facility

The first project is being implemented by TOO „ForYou Energy“ with investments of $175 million. It is an investment cooperation project between Kazakhstan and South Korea. The facility is designed to process up to 900 tons of solid municipal waste per day and generate up to 20 megawatts of electricity. Construction is divided into two phases: the first phase is scheduled for the first quarter of 2027, and the second for the third quarter of 2029. During construction, 400 jobs will be created, followed by 200 permanent positions after commissioning.

Steel plant and Chinese participation

The second project is realized through a joint venture between TOO „Tarazsky proizvodstvenny kombinat“ and the Chinese company Guangdong Wantai Supply Chain Co., Ltd. The investment volume is $130 million (according to other sources, ₸61 billion or $129 million). The plant will produce up to one million tons of metal products annually, including hot-rolled steel coils, stainless steel products, welded and galvanized pipes, and rebar. The launch of the first phase is planned for the first quarter of 2028. 500 jobs are expected during construction, with 260 permanent positions created after operation begins.

Regional investment climate

The region saw a 59.2 percent increase in investments in fixed capital in the first half of 2026, reaching ₸505.9 billion. Direct foreign investments in the first quarter of 2026 stood at $333.2 million, exceeding the annual plan of $315 million ahead of schedule. Currently, the region's investment pool includes 116 projects with a total value of ₸5.6 trillion, 71 of which are under construction.

Project: Taldyqorghan Industrial Zone: Waste Recycling and Steel Plant · Kazakhstan · Under construction · $305 m

Key facts

  • Total volume of both projects: $305 million
  • Waste recycling plant: $175 million investment, Phase 1 start: Q1 2027
  • Steel plant: $130 million investment, Phase 1 start: Q1 2028
  • Steel plant capacity: up to 1 million tons of metal products per year
  • Waste plant capacity: 900 tons of waste/day, 20 MW electricity
  • Jobs: 400 (construction waste) + 200 (permanent waste) + 500 (construction steel) + 260 (permanent steel)

All sources (7)

  1. В Жамбылской области началось строительство двух крупных заводов на $305 млнKapital.kz (Telegram) · · RU
  2. Инвестиции на $305 млн: в Жамбылской области началось строительство двух крупных заводовgov.kz · · RU
  3. Металлургический завод за ₸61 млрд начали строить в ТаразеKapital.kz · · RU
  4. 投资3.05亿美元!江布尔州两座大型工厂开工建设哈通社 · · ZH
  5. Казахстан начал строительство меткомбината в промышленно...GMK Center · · RU
  6. Kazakhstan has begun construction of a steel complex in the Taraz industrial zone, at a cost of $129 millionGMK Center · · EN
  7. Заводы за $305 млн построят в Жамбылской областиMyBuh.kz · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn