A consortium of companies belonging to China National Chemical Engineering Group has signed a project cooperation agreement with a Kazakh copper company to modernise the Zhezkazgan copper smelter. The contract is worth $213.76 million. Its core is a new sulphuric acid plant with a design capacity of 350,000 tonnes per year. Trial operation is planned for 2028.
The project is being carried out as an EPC contract, with the Chinese consortium responsible for design, procurement and construction. Large-scale site mobilisation and preparatory work are to start before the end of 2026. This is to be followed by a construction and installation phase of about 29 months.
The Kazakh company is a vertically integrated group in mining and non-ferrous metal smelting. It produces 271,000 tonnes of copper concentrate a year, ranking 20th worldwide, and 377,000 tonnes of blister copper and 365,000 tonnes of cathode copper, ranking 12th worldwide in both. The smelter's off-gas treatment system was built in the 1970s, and its sulphur dioxide emissions are a threat hanging over local residents. The main reason for the upgrade is tightening environmental regulation: the old system has been in service for more than fifty years, captures gas inefficiently and frequently breaks down, disrupting continuous production.
Besides a complete new sulphuric acid plant, the existing gas capture and cleaning systems will be fully modernised. The equipment list includes converter hoods, new cooling towers, electrostatic precipitators and other dust removal and desulphurisation units. Automated control and process management systems will also be installed. The acid plant can handle up to 300,000 standard cubic metres of process gas per hour, enough for the maximum gas volume at full smelter output.
After completion, the capture rate for process gases is expected to rise to 99 percent. Sulphur dioxide concentrations in the treated exhaust gas are to meet the requirements of the international best available techniques reference documents. The captured sulphur dioxide will be converted into industrial sulphuric acid, which in Kazakhstan and Central Asia is an important raw material for phosphate fertiliser and chemical production with stable demand.
Project: Zhezkazgan copper smelter sulphuric acid plant · Kazakhstan · Agreed · $214 m
Key facts
- Contract value: US$213.76 million
- Capacity: 350,000 t of sulphuric acid per year, up to 300,000 Nm³ of process gas per hour
- Gas capture rate to rise to 99%
- Mobilisation by end-2026, about 29 months of construction, trial operation in 2028