Alatau: Infrastructure deficits and supply bottlenecks in newly incorporated settlements

The smart city of the future between Almaty and Konaev – put into context for European companies

· 2 Sources

Scroll
Construction & infrastructure2 Sources

Published · last updated · 19 Jun 2024 – 20 Jun 2024

One year after the official establishment of the new city of Alatau from several villages, residents of the incorporated areas continue to complain about inadequate basic services. There are significant deficits in electricity and water supply, road conditions, and digital infrastructure.

Key facts

  • The city of Alatau was formed in January 2024 from the villages of Jetigen, Zhana Arna, Enbek, and Kuigan (area: 88,000 ha).
  • In parts of Enbek (e.g., Aralyk Street), there is no electricity grid; residents use private wiring.
  • The gas connection fee at TOO "Er-Kai" in Koyankus is over 1 million tenge, compared to 350,000–400,000 tenge in neighboring settlements.
  • Access to the Kapshagai highway in Koyankus is blocked by private construction; alternative route via a closed bridge.
  • Bridge repair in Koyankus is scheduled for completion by October 2024.

All sources (2)

  1. Нет света, нет дорог, нет нормальной школы. Так живут в новом городе Алатау, бывшем селе ЕнбекOrda.kz · · RU
  2. Почему жители города Алатау добираются до работы через кладбищеInformburo.kz · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn